건설 프로젝트 공기 지연 발생에 영향을 미치는 주요 요인 분석

Key Factors Influencing Construction Project Schedule Delays
  • 이사롤; 
  • 전영훈; 
  • 이종호; 
  • 최용석; 
  • 김규형; 
  • ... 김진우; 
  • 외 1명

초록

Delays in construction project schedules are a critical concern, as they often lead to cost overruns, quality issues, and contractual disputes, significantly impacting project success. While existing research primarily focuses on specific processes or types of work, their limited scope may not fully capture the broader context. This study aims to address this gap by comprehensively analyzing factors contributing to construction schedule delays, using real-world cases from building and civil engineering projects with documented schedule extensions, alongside a review of existing literature. The relative impact of these factors was assessed through the Analytic Hierarchy Process (AHP), based on survey responses from construction scheduling experts. The findings reveal that "work stoppages (external factors)" are the most significant contributors, with "labor strikes" and "material supply delays" emerging as critical sub-factors. Notably, "delays caused by raw material price increases" were identified as having the highest weight, emphasizing their critical influence. This study highlights the importance of developing effective strategies to address these key delay factors and mitigate their impact on project schedules.

키워드

건설 프로젝트; 공기 지연; 리스크 요인; 계층적 분석; 연장 사례; 스케줄링 전문가; Contsruction project; Schedule delay; Risk factor; AHP; Delayed cases; Scheduling experts
제목
건설 프로젝트 공기 지연 발생에 영향을 미치는 주요 요인 분석
제목 (타언어)
Key Factors Influencing Construction Project Schedule Delays
저자
이사롤; 전영훈; 이종호; 최용석; 김규형; 전정호; 김진우
DOI
10.5659/JAIK.2025.41.10.329
발행일
2025-10
유형
Y
저널명
대한건축학회논문집
권
41
호
10
페이지
329 ~ 337